Ashley Road Depot logoAshley Road Depot

Milestones

We are seeking to redevelop the Ashley Road Depot site, to build new council homes and create new green links to Down Lane Park. Residents are being asked for their views about our revised proposals; a first stage of community engagement was carried out in October and has helped shaped the revised proposals. We aim to use your views to inform our final planning application, expected in early 2022.
  • Phase 1 of Community Engagement

    October 2021

     

    -

     

    Complete

    Presented initial redevelopment proposals -- listened to residents' feedback
  • Phase 2: Detailed design and further public engagement

    November 2021

     

    -

     

    January 2022

    Shared with residents more detailed design proposals, building on their earlier feedback -- with in-person and online engagement events.
  • Demolition works

    January 2022

     

    -

     

    June 2022

    Demolition work to remove the old buildings and hoarding to help secure the site from trespassers.
  • Planning submission

    16 March 2022

     

    -

     

    Complete

    Develop and submit a planning submission, informed by residents' feedback.
  • Public Consultation on Planning Application

    16 March 2022

     

    -

     

    02 May 2022

    Public consultation on the planning application.
  • Planning Committee recommends approval

    11 July 2022

     

    -

     

    Complete

    Haringey's planning committee recommends approval for our proposals
  • Site Preparation

    Spring 2023

     

    -

     

    In Progress

    Site to be prepared for construction works
  • Construction

    Summer 2023

     

    -

     

    Upcoming

    Commencement of construction works
  • Completion of New Homes

    Spring 2026

     

    -

     

    Upcoming

    Milestone description